7th Street South & 13th Avenue South Resurfacing

2017-PV056-7th-St-S-&-13th-Ave-S-webmap-4-21-17.gif

Project Details

Project Type:
Asphalt Resurfacing Project

Project Location:
7th Street South, from 11th Avenue South to 13th Avenue South;
and 13th Avenue South, from 5th Street South to 8th Street South

Construction Start Date:
May 2017

Duration of Construction:
Concrete replacement under traffic will take 2 weeks.

Asphalt mill and overlay work will take 2 days during which the westbound ramp from Hiawatha Avenue will be closed.

Meetings

Pre-Public Hearing
6:30 p.m., Monday, March 6, 2017
Elliot Recreation Center
1000 E 14th Street

Formal Public Hearing
9:30 a.m., Tuesday, March 14, 2017
Council Chambers, City Hall
350 South 5th Street, 3rd Floor

 

Contact: Chris Trembath, 612-919-1196 or chris.trembath@minneapolismn.gov

 

 

(Note: Project information may change due to scheduling, weather, or other factors outside of our control. Listings will be updated as new information becomes available.) Citizens concerned with pedestrian access during construction should contact the project manager directly.